McDonald & Ross Const. Ltd. was contracted by Trans Mountain for the HDPE Pipe Install/Fire System Upgrades at the Burnaby Tank Farm.
The Project included:
•	Placement of BC Call One
•	On Site pre-construction meeting
•	Mobilization to site
•	Marking out running line
•	Locating foreign utilities 
•	Re-grading at Pump House
•	Stringing out pipe
•	Fusing pipe
•	Trenching excavation
•	Lowering in fused sections
•	Assembling hydrants and valves
•	Air testing in sections
•	Backfilling 
•	Final Air Test
•	Restoration and Site Clean Up
•	Demobilization